Aviano Development Project

5 Documents in Project

Summary

SCH Number
2006072024
Lead Agency
City of Antioch
Document Title
Aviano Development Project
Document Type
NOD - Notice of Determination
Received
Posted
4/13/2015
Present Land Use
LU: vacant grazing land; segment of Sand Creek; PG&E transmission line easement and several natural gas pipelines; Off-site impact to grazing and agricultural lands GP: Sand Creek Focus Area; Low Density Residential; Multiple Family Residential; Public/Quasi Public; Hillside Estate;Executive Residential or Open Space Z: Study District
Document Description
The Central Valley Water Board is issuing a 401 Water Quality Certification for this project. The project consists of constructing an adult residential development. Construction is only planned north of Sand Creek. A new bridge on the proposed Sand Creek Road extension will cross Sand Creek at the south side of the Project site. The Sand Creek Road extension will parallel Sand Creek to the west. Runoff from the proposed development site will enter two new storm water basins to the north of Sand Creek, treated, and hyrdo-modified before being discharged into Sand Creek through a single outfall structure. Fill, excavation, and dredging activities will impact waters of the United States.

Contact Information

Name
Stephanie Tadlock
Agency Name
Central Valley Regional Water Board
Contact Types
Lead/Public Agency

Location

Cities
Antioch
Counties
Contra Costa
Cross Streets
Hillcrest Avenue / Prewett Ranch Drive
Zip
94531
Total Acres
214
Parcel #
057-050-013 and 057-030-001
State Highways
Highway 4
Railways
SPRR
Schools
Several
Waterways
Sand Creek, Marsh Creek, Deer Creek

Notice of Determination

Approving Agency
Central Valley Regional Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes