Imperial Promenade

2 Documents in Project

Summary

SCH Number
2006071020
Lead Agency
City of La Habra
Document Title
Imperial Promenade
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2006
Present Land Use
Z: C2-S PUD - Community Shopping Center, Planned Unit Development (PUD). The project is also located within the Delta One Redevelopment Area.
Document Description
The project site was previously occupied by a Super K-Mart store, which has subsequently been vacated. The project proposes to utilize the existing commercial structure for shopping center tenants by partitioning the interior, enclosing the uncovered portions of the garden center for retail space and updating the architectural elements on the exterior of the building. In addition, two new development pads will be constructed with free-standing buildings to accommodate additional commercial tenants. The vacated building contains a total floor area of 182,983 square feet. The proposed additional commercial development would result in a maximum total building floor area of 218,321 square feet. The parking and landscape areas will also be upgraded and enhanced to improve the aesthetic quality of the project site.

Contact Information

Name
Carlos Jaramillo
Agency Name
City of La Habra
Contact Types
Lead/Public Agency

Location

Cities
La Habra
Counties
Orange
Cross Streets
Idaho Street and Imperial Highway
Zip
90631
Total Acres
17
Parcel #
019-171-19
State Highways
90 and 39
Airports
Fullerton Airport
Schools
La Habra City School District, Lowell Joint School District, Ful
Other Information
Schools: Fullerton Joint HS District.

Notice of Determination

Approving Agency
City of La Habra
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.