Moua Immediate Rezone of Timberland Production Zone

3 Documents in Project

Summary

SCH Number
2006052145
Lead Agency
Del Norte County
Document Title
Moua Immediate Rezone of Timberland Production Zone
Document Type
NOD - Notice of Determination
Received
Posted
7/2/2009
Document Description
Rezone of 21.33 acres from a TPZ (20 acre minimum lot size) zone designation to a Rural Residential-3 acres minimum lot size zone designation. The parcel is located on the west side of Wonder Slump Road between Ecnav Lane and Sorrel Ridge Road. A concurrent application to subdivide the 21.33 acre parcel into 3 parcels ~8.0 acres, 7.0 acres and 6.11 acres has been filed. Approval of the subdivision is contingent upon Board of Supervisors and State Board of Forestry approval of removal of the land from a TPZ designation. The General Plan Land Use designation for the parcel if Rural Residential-one dwelling unit per 3 acres. The parcel is developed with one single family residence that is served with a public water connection and an on-site sewage disposal system. Future development on the proposed undeveloped parcels would have similar utilities. Several wetlands and drainage areas exist on-site and will be protected through buffers to development.

Contact Information

Name
Heidi Kunstal
Agency Name
Del Norte Planning Commission
Contact Types
Lead/Public Agency

Location

Cities
Crescent City
Counties
Del Norte
Cross Streets
WonderStump Road, South of Ecnay Lane
Zip
95531
Parcel #
106-191-24
State Highways
101
Schools
Sunset HS
Waterways
Younkers Creek
Township
17N
Range
1W
Section
35
Base
HBM

Notice of Determination

Approving Agency
Del Norte County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print