Sacramento Voltage Support Transmission Line Project

5 Documents in Project

Summary

SCH Number
2006052119
Lead Agency
Sacramento Municipal Utility District
Document Title
Sacramento Voltage Support Transmission Line Project
Document Type
NOD - Notice of Determination
Received
Posted
12/23/2009
Document Description
The proposed project consists of the following components: 1. Constructing a new, double-circuit 230-kilovolt (kV) transmission line between O-Banion Substation and the area just south of the Elverta Substation. This transmission line would include a new circuit from O'Banion Substation to Elverta Substation and a new circuit from O'Banion Substation to Natomas Substation. 2. Reconstructing the existing double-circuit 230-kV/115-kV transmission line between Elverta Substation and Natomas Substation into a double-circuit 230-kV transmission line.

Contact Information

Name
Paul Thayer
Agency Name
California State Land Commission
Contact Types
Lead/Public Agency

Location

Cities
Marysville, Roseville, Sacramento
Counties
Placer, Sacramento, Sutter
Cross Streets
Highway 99, Riego Road, Elverta Road, Elkhorn Boulevard, East Levee Road
Parcel #
Linear project over about 40 miles
State Highways
99, 70, I-5, I-80
Railways
Union Pacific
Airports
Sacramento International
Schools
Elverta Joint Elementary School
Waterways
Feather River, numerous creeks and canals

Notice of Determination

Approving Agency
California State Lands Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.