Construction of a Water Transmission Pipeline for the Marina Del Rey Community

3 Documents in Project

Summary

SCH Number
2006051094
Lead Agency
Los Angeles County
Document Title
Construction of a Water Transmission Pipeline for the Marina Del Rey Community
Document Type
NOD - Notice of Determination
Received
Posted
2/2/2011
Present Land Use
Residential, Hotel, Marine Commercial
Document Description
The Los Angeles County Department of Public Works, on behalf of the Marina del Rey Water System, is proposing to install approximately 20,000 feet of new 18-inch-diameter steel pipeline to replace the existing old and undersized 10- to 14-inch-diameter water main that currently forms a loop around Marina del Rey. The project represents Phases II and III of a Water System Improvement Master Plan for the Marina del Rey Water System. Phase II will consists of installing approximately 9,500 linear feet of water main along Via Marina, Admiralty Way, and portions of Fiji Way. Phase III will consist of installing approximately 9,800 linear feet of water main along Via Marina, Bora Bora Way, and Fiji Way.

Contact Information

Name
Eleni Hailu
Agency Name
Los Angeles County
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles, Los Angeles, City of, Santa Monica, Santa Monica
Counties
Los Angeles
Cross Streets
Via Marina, Washington Blvd., Admiralty Way, Fiji Way
Zip
90292
State Highways
1, 42, 90, 187
Airports
LAX
Schools
Short Ave ES, Antioch University
Waterways
Ballona Creek, Sepulveda Channel, Venice Cannal
Other Location Info
City/Nearest Community: Marina del Rey

Notice of Determination

Approving Agency
CA Department of Public Works
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print