Issuance of California Endangered Species Act Incidential Take Permit 2081-2010-004-06 (ITP) Major Amendment 1

6 Documents in Project

Summary

SCH Number
2006051008
Lead Agency
Caltrans 8 (San Bernardino) (California Department of Transportation, District 8)
Document Title
Issuance of California Endangered Species Act Incidential Take Permit 2081-2010-004-06 (ITP) Major Amendment 1
Document Type
NOD - Notice of Determination
Received
Posted
2/5/2013

Document Description
This proposed project involves the construction of a full-service interchange where La Mesa Road to the east and Nisquali Road to the west currently terminate at I-15. A two-span over-crossing will convey six lanes of local street traffic over I-15. Existing frontage roads (Amargosa Road on the west and Mariposa Road on the east) will be relocated away from I-15 to accommodate the implementation of interchange ramps on approximately 10.93 acres of Mohave ground squirrel habitat.

Contact Information
Kimberly Nicol
Department of Fish and Wildlife
Inland Deserts Region 3602 Inland Empire Boulevard, Suite C-220
Ontario, CA 91764

Phone : (909) 484-0459

Location

Cities
Victorville
Counties
San Bernardino
Cross Streets
La Mesa and Nisqualli Road
State Highways
I-15
Airports
Southern CA Logist. & Hesperia
Schools
Victor Valley Christian Elementary School
Waterways
Oro Grande Wash

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
California Department of Transportation 464 W. Fourth Street, San Bernardino, CA 92401

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search