Water Tank Installation Project

2 Documents in Project

Summary

SCH Number
2006032004
Lead Agency
California Department of Parks and Recreation
Document Title
Water Tank Installation Project
Document Type
NOD - Notice of Determination
Received
Posted
4/12/2006
Present Land Use
Open Space
Document Description
The Department of Parks and Recreation proposes to replace the deteriorating potable water storage tanks at Samuel P. Taylor State Park to provide reliable and adequate supplies for park use and fire protection. The project will replace two 40 year old 100,000-gallon redwood storage tanks with two 210,000-gallon steel tanks - Main Tank and Barnabe Tank. The following is a brief summary of the proposed work: - Remove the existing redwood tanks. The existing redwood material and metal will be stored at the Park for potential reuse. The Barnabe tank will be replaced first. - Perform ground excavation, grading and compaction required for construction of the new tanks. - Construct two new 210,000-gallon steel water storage reservoirs on-site. - Perform final grading, roadwork, and landscape improvements as necessary to provide access for maintenance, and restoration of the surrounding natural resources. - Provide equipment staging areas: near the park residences adjacent to Lagunitas Creek and on the leve area downhill from the Barnabe tank site.

Contact Information

Name
Patricia DuMont
Agency Name
California Department of Parks and Recreation
Contact Types
Lead/Public Agency

Location

Counties
Marin
Cross Streets
Sir Francis Drake Boulevard
Zip
94938
State Highways
Hwy. 1
Waterways
Lagunitas Creek
Other Location Info
City/Nearest Community: Lagunitas

Notice of Determination

Approving Agency
California Department of Parks and Recreation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.