Folsom Dam Safety and Flood Damage Reduction-Early Approach Channel Excavation
30 Documents in Project
Summary
SCH Number
2006022091
Lead Agency
Central Valley Flood Protection Board
Document Title
Folsom Dam Safety and Flood Damage Reduction-Early Approach Channel Excavation
Document Type
NOD - Notice of Determination
Received
Posted
10/15/2009
Document Description
Early construction of portions of an approach channel to the new spillway under construction at Folsom Dam that can be constructed "in the dry", during low water levels in Folsom Lake, thereby avoiding environmental impacts and costs.
Contact Information
Name
Annalena Bronson
Agency Name
Central Valley Flood Protection Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Folsom
Counties
Sacramento
Cross Streets
Folsom Lake Crossing near Natoma at Blue Ravine
Zip
95630
Waterways
American River/Folsom Lake
Notice of Determination
Approving Agency
Central Valley Flood Protection Board
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes