Folsom Dam Safety & Flood Damage Reduction - Prison Staging Area & Stilling Basin Drain
30 Documents in Project
Summary
SCH Number
2006022091
Lead Agency
Central Valley Flood Protection Board
Document Title
Folsom Dam Safety & Flood Damage Reduction - Prison Staging Area & Stilling Basin Drain
Document Type
NOD - Notice of Determination
Received
Posted
10/2/2012
Document Description
This Supplemental Environmental Assessment / Environmental Impact Report discusses in detail and evaluates the refinements for: 1) using 10 acres of Folsom State Prison land for staging and operating a concrete batch plant, 2) installing a temporary traffic signal on Folsom Lake Crossing, 3) widening an existing dirt access road, and 4) constructing a drain at the stilling basin.
Contact Information
Name
Vincent Heim
Agency Name
Central Valley Flood Protection Board
Contact Types
Lead/Public Agency
Phone
Location
Notice of Determination
Approving Agency
Central Valley Flood Protection Board
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.