Precise Plan of Design No. 2005-0009; Loma Linda University Centennial Complex

3 Documents in Project

Summary

SCH Number
2005111025
Lead Agency
City of Loma Linda
Document Title
Precise Plan of Design No. 2005-0009; Loma Linda University Centennial Complex
Document Type
NOD - Notice of Determination
Received
Posted
1/18/2006
Present Land Use
Institutional Z: Institutional GP: Institutional
Document Description
A request to demolish the existing Gentry Gym (approximately 22,500 square feet) and construct (1) a four-story, 148,000 square-foot building to include: an anatomy lab, teaching laboratories, smart classrooms, Global Gateway Technology Center, and faculty office (completed within approximately 24 months); (2) a 157,524 square-foot Learning Center (constructed sometime within the next five to ten years); and (3) a 21,257 square-foot student services building (constructed sometime within the next five to ten years) and also includes the construction of a three-story parking structure, resurfacing of the existing parking lot, a thermal energy storage tank, and construction of a central electrical plant substation at the existing Electrical Yard/House Keeping facility.

Contact Information

Name
H. P. Kang
Agency Name
City of Loma Linda
Contact Types
Lead/Public Agency

Location

Cities
Loma Linda, San Bernardino
Counties
San Bernardino
Cross Streets
Anderson Avenue
Zip
92354
Total Acres
~ 18
Parcel #
0283-071-31, 35, 43
State Highways
10
Railways
Pacific RR
Schools
Loma Linda Academy

Notice of Determination

Approving Agency
City of Loma Linda
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.