California Correctional Center Wastewater Treatment Plant Improvement Project

3 Documents in Project

Summary

SCH Number
2005102005
Lead Agency
California Department of Corrections and Rehabilitation (CDCR)
Document Title
California Correctional Center Wastewater Treatment Plant Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
6/12/2006
Present Land Use
Institutional / Upland Conservation and Extensive Agriculture
Document Description
The proposed CCC WWTP improvement project would enhance treatment facilities at the CCC WWTP to improve discharge effluent quality in compliance with the California Regional Water Quality Control Board, Lahontan Region permit requirements. The CCC WWTP system is currently permitted to treat an average dry weather flow of 1.4 million gallons per day (mgd), and is currently permitted to discharge 1.0 million mgd via land disposal onto irrigated row crops. The proposed project would increase the facility's permitted treatment and discharge capacity to 1.8 mgd. Proposed facilities include the proposed acquisition of a 640-acre parcel of land that would accommodate a new 270-acre irrigation spray field and a buffer zone around the spray field. Project improvements include constructing two storage ponds, converting two sedimentation ponds to aeration ponds, constructing two storage ponds, converting two sedimentation ponds and new sludge drying beds, installing parallel influent force main, and improvements to the plant head works. The proposed facility would be located within the existing CCC property boundary and will be operated by existing plant operations staff.

Contact Information

Name
Cher Daniels
Agency Name
Department of Corrections and Rehabilitation
Contact Types
Lead/Public Agency

Location

Cities
Susanville
Counties
Lassen
Cross Streets
Center Road and Rice Canyon Road
Zip
96127
State Highways
395
Railways
SPRR
Waterways
Susan River

Notice of Determination

Approving Agency
California Department of Corrections and Rehabilitation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.