Extension of 42" Milliken Avenue Transmission Main, Two Pressure Reducing Stations, One Inter-Agency Connection, and a 24" Phillips Street Zone Transmission Mai

2 Documents in Project

Summary

SCH Number
2005101114
Lead Agency
City of Ontario
Document Title
Extension of 42" Milliken Avenue Transmission Main, Two Pressure Reducing Stations, One Inter-Agency Connection, and a 24" Phillips Street Zone Transmission Mai
Document Type
NOD - Notice of Determination
Received
Posted
1/24/2006
Present Land Use
Planned Commercial, Community Commercial, Non-Recreational Open Space, Business Park, One-Family Residential, Specific Plan Ag Reserve, Open Space, Manufacturing - Service Commercial
Document Description
The proposed project is to construct Phase 1 and Phase 2A of Ontario's New Model Colony Francis Street Zone Water System. As recommended by the City of Ontario Water Master Plan (August 2002), and as identified in the SOI (New Model Colony), FEIR (October 1997), SCH# 1997061035, it is necessary to construct new distribution system facilities to supply water to the New Model Colony. As part of the Water Master Plan, these improvements have been identified to help meet the current and future water demand of the New Model Colony Area.

Contact Information

Name
Fernando E. Cobos
Agency Name
City of Ontario
Contact Types
Lead/Public Agency

Location

Cities
Ontario
Counties
San Bernardino
Cross Streets
Milliken Avenue & Riverside Drive
Zip
91761
Total Acres
~ 10
Parcel #
Various
State Highways
I-15, I-10, I-60
Railways
Numerous
Airports
Ontario Airport
Schools
Mountain View SD, Chaffey Joint Union High SD
Waterways
Santa Ana River
Township
1S, 2S
Range
7W
Section
25, 26
Base
SBBM

Notice of Determination

Approving Agency
Ontario City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print