Seacoast Inn Specific Plan

3 Documents in Project

Summary

SCH Number
2005101113
Lead Agency
City of Imperial Beach
Document Title
Seacoast Inn Specific Plan
Document Type
NOD - Notice of Determination
Received
Posted
12/13/2007
Present Land Use
Seacoast Commercial Zone (C-2) is a visiting center, pedestrian- oriented commercial area (specialty stores, surf shops, restaurants, hotels, etc.)
Document Description
This is an application (MF 661) by Imperial Coast Limited Partnership (owner)/Pacifica Companies (applicant) for a Regular Coastal Permit (CP 03-091), a Tentative Map (TM 03-092), Site Plan Review (SPR 03-093), Design Review (DRC 03-094), a Specific Pplan (GPA 03-095), and an Environmental Impact Report (EIR 04-034) to demolish the existing 3-story 38-room Seacoast Inn Hotel and Timber seawall and redevelop the site as a 78-room hotel, 40 feet high with 111 parking spaces in a subterranean garage, a restaurant, swimming pool, meeting rooms, and a new vertical seawall to be located 35' east of the existing seawall along with enhanced street end improvements to Date Ave. with its new vertical seawall.

Contact Information

Name
Jim Nakagawa
Agency Name
City of Imperial Beach
Contact Types
Lead/Public Agency

Location

Cities
Imperial Beach
Counties
San Diego
Cross Streets
Daisy Avenue to north, Date Avenue to south; Seacoast Drive (800)
Zip
91932
Total Acres
1.39
Parcel #
625-262-01-00
State Highways
SR-75
Airports
Naval Outlying Landing Field
Schools
Imperial Beach ES
Waterways
Pacific Ocean, Tijuana River National Wildlife Refuge

Notice of Determination

Approving Agency
City of Imperial Beach
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print