Well 6807-1
3 Documents in Project
Summary
SCH Number
2005101017
Lead Agency
Coachella Valley Water District
(CVWD)
Document Title
Well 6807-1
Document Type
NOD - Notice of Determination
Received
Posted
11/17/2005
Present Land Use
Agricultural
GP: Agricultural
Document Description
This project includes drilling, casing, testing, and developing a 2,000 gallon-per-minute domestic water well including the installation of a 300-horsepower motor, a 2,000 gallon-per-minute pump, and other aboveground and underground appurtenances required to connect the well and pumping plant into the domestic water distribution system. An additional 1,500 feet of 12-inch pipe will be installed to connect Well 6807-1 to Well 6806-1 and arsenic facility site located in the southwest corner of the Pierce Street/Avenue 60 intersection. The Well 6807-1 site will be surrounded by a 6-foot-high masonry wall. The purpose of the Well 6807-1 project is to provide domestic water service to the Mecca Pressure Zone and serve as a backup source of water to Area 23. Area 23 includes North Shore, Bombay Beach, and Hot Mineral Spa.
Contact Information
Name
Luke Stowe
Agency Name
Coachella Valley Water District
Contact Types
Lead/Public Agency
Phone
Location
Counties
Riverside
Cross Streets
Avenue 60 / Pierce Street
Zip
92254
Total Acres
0.50
State Highways
SR 86, SR 111
Airports
Thermal Airport
Waterways
All-American Canal
Township
6S
Range
8E
Section
25
Base
SB
Other Location Info
City/Nearest Community: Mecca
Notice of Determination
Approving Agency
Coachella Valley Water District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.