FIS Improvements - Addendum to the Final EIR for the San Diego International Airport Master Plan

15 Documents in Project

Summary

SCH Number
2005091105
Lead Agency
San Diego County Regional Airport Authority
Document Title
FIS Improvements - Addendum to the Final EIR for the San Diego International Airport Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
3/6/2017
Present Land Use
International Airport/International Airport
Document Description
Construction & operation of expanded Federal Inspection Services (FIS) facility, increasing capacity as part of the Airport Implementation Plan (evaluated in the 2008 FEIR at a Project-level analysis). Includes facilities for international passengers (i.e., the federal inspection of arriving international passengers: Customs & Border Patrol, baggage claim, & U.S. Dept. of Agriculture). The current FIS facility, located in T2E, has reached capacity & must be replaced. FIS is to be relocated to the existing T2W. Pursuant to Section 15162 of CEQA Guidelines, an Addendum to the 2008 FEIR was prepared & considered along with the 2008 FEIR in approving the project.

Contact Information

Name
Ted Anasis
Agency Name
San Diego County Regional Airport Authority
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
North Harbor Drive; Pacific Highway and Sassafrass Street
Zip
92101
State Highways
I-5
Railways
BN&SF
Airports
San Diego International
Waterways
San Diego Bay

Notice of Determination

Approving Agency
San Diego County Regional Airport Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print