Wilton Road Culvert Replacement Project
3 Documents in Project
Summary
SCH Number
2005082070
Lead Agency
City of Elk Grove
Document Title
Wilton Road Culvert Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
10/7/2005
Present Land Use
The proposed project area lies in the eastern portion of the City of Elk Grove near the Sacramento County boundary. The City of Elk Grove General Plan Land Use Policy map designates the area north of the project site as rural residential. Sacramento County General Plan Land Use Diagram designates the area south of the project site as agricultural cropland. The areas immediately adjacent to the proposed project site are used as rural residential to the north and recreational to the south.
Document Description
The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement number 1600-2005-0337-R2 pursuant to Section 1602 of the Fish and Game Code to the project applicant, City of Elk Grove.
Project pertains to the replacement of an existing 60-inch CMP culvert beneath Wilton Road with two 7-foot by 5-foot concrete box culverts or the equivalent hydraulic capacity.
Contact Information
Name
Gary L. Hobgood
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Elk Grove
Counties
Sacramento
Cross Streets
Approximately 1,800 feet SE of Grant Line Road/Wilton Road intersection on Wilton Road
Railways
Central CA Traction Co Railroad
Waterways
Cosumnes River, Deer Creek, Laguna Creek, Clark Lake
Township
7N
Range
6E
Section
26
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.