Terminal B Parking Garage

17 Documents in Project

Summary

SCH Number
2005082017
Lead Agency
Sacramento County
Document Title
Terminal B Parking Garage
Document Type
NOD - Notice of Determination
Received
Posted
8/1/2023
Document Description
The proposed Terminal B Parking Garage is planned to provide the near-term parking needs for SMF. The proposed location for the garage is west of Terminal B, over the existing surface Hourly B Lot. The project will connect the new garage to the existing five-story elevator tower that leads into Terminal B via an elevated pedestrian walkway. The parking garage will have up to 5,500 parking spaces across five floors, with a footprint of approximately 7 acres. The concept plan shown in has access roads and a toll plaza. These are approximate locations and likely will be rearranged as the construction plans are solidified. Some of the parking surrounding the new Terminal B Parking Garage may be modified to accommodate the new access road and toll plaza. However, efforts will be made to not reduce the number of existing parking spaces. The proposed parking garage, location and disposition is consistent with the 2020 Sacramento International Airport Master Plan Update approved by the Sacramento County Board of Supervisors on February 16, 2022.

Contact Information

Name
Julie Newton
Agency Name
Sacramento County Planning
Job Title
ENVIRONMENTAL COORDINATOR
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Regions
Countywide
Parcel #
Portions of: 201-0240-041-0000, 201-0240-019-000, 201-0240-038-0000

Notice of Determination

Approving Agency
Sacramento County Planning
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
https://planningdocuments.saccounty.net/

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print