South Bay Power Plant Below Ground Demolition of In-Water Structures (Chula Vista Bay front Master Plan)

18 Documents in Project

Summary

SCH Number
2005081077
Lead Agency
San Diego, Port of
Document Title
South Bay Power Plant Below Ground Demolition of In-Water Structures (Chula Vista Bay front Master Plan)
Document Type
NOD - Notice of Determination
Received
Posted
9/2/2014
Document Description
The San Diego Regional Water Quality Control Board is issuing a Clean Water Act Section 401 water quality certification (Cert. No. R9-2014-0028) to the project applicant, Dynegy South Bay, LLC. The applicant proposes to remove in-water structures associated with the South Bay Power Plant within tidal waters of San Diego Bay. The voids left by removing the intake structures will be filled in to match the slope and substrate of the adjacent shoreline. The remaining structures will be removed by crane with minimal impact to the shoreline and bay floor, with the exception of four discharge structures, which will be structurally sealed in place.

Contact Information

Name
Lesley Nishihira
Agency Name
RWQCB - San Diego Region
Contact Types
Lead/Public Agency

Location

Cities
Chula Vista
Counties
San Diego
Cross Streets
Bay Boulevard, Marina Parkway, E Street, H Street, J Street, L Street
Zip
91910
Total Acres
556-land & water
Parcel #
Multiple
State Highways
I-5
Railways
SD&AE, MTS Trolley
Schools
Mueller, Vista Square, Feaster Edison, and Harborside
Waterways
San Diego Bay, Sweetwater River, Telegraph Canyon Channel
Township
18S
Range
2W
Section
NC/IB
Base
USGS

Notice of Determination

Approving Agency
RWQCB - San Diego Region
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes