Chevron Revised Energy and Hydrogen Renewal Project

4 Documents in Project

Summary

SCH Number
2005072117
Lead Agency
City of Richmond
Document Title
Chevron Revised Energy and Hydrogen Renewal Project
Document Type
NOD - Notice of Determination
Received
Posted
8/11/2008
Present Land Use
M-3 Heavy Industrial / Heavy Industrial
Document Description
The Chevron Richmond Refinery (the Refinery) is located at 841 Chevron Way in the City of Richmond. This Master Environmental Conditional Use Permit No. 1101974/Design Review Permit No. 1104423 and Conditions of Approval thereto allowing Chevron Products Company to replace the existing Hydrogen Plant, Power Plant, Catalytic Reformer and tanks; and install new equipment, including Hydrogen Purity Improvements, storage tanks, central control room and maintenance facility; involving modifying, replacing and installing typical refinery equipment, all within the boundaries of the Chevron Richmond Refinery, in order to increase the Refinery's ability to produce gasoline that meets California specifications, and use a wider range of crude oil sources than are currently processed. The new equipment would improve Refinery reliability, energy efficiency, and add environmental controls. Associated community benefits agreement.

Contact Information

Name
Lamont Thompson
Agency Name
City of Richmond
Contact Types
Lead/Public Agency

Location

Cities
Richmond
Counties
Contra Costa
Cross Streets
Castro Street
Zip
94804
Total Acres
2,900
Parcel #
561-100-002
State Highways
580
Railways
Santa Fe Railyards
Waterways
San Pablo Bay and San Francisco Bay

Notice of Determination

Approving Agency
City of Richmond
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.