Steam Expansion Phase 1 Project

2 Documents in Project

Summary

SCH Number
2005072013
Lead Agency
University of California, Davis
Document Title
Steam Expansion Phase 1 Project
Document Type
NOD - Notice of Determination
Received
Posted
11/18/2005
Present Land Use
Support Facilities
Document Description
The Steam Expansion Phase I project includes a 7,532 gross square feet addition to the Central Heating and Cooling Plant (CHCP) that will add one 150,000 pounds per hour boiler and appurtenances to the existing Central Plant. The additional steam capacity will be used for building heating needs and process heating demand from specialized equipment. The added steam generation is designed to provide adequate capacity to meet the projected peak steam demand through the winter of 2011. The project also includes a 15 foot high, 66,000 gallon on-grade fuel storage tank to be located within the existing 10-foot high concrete walls of the CHCP compound.

Contact Information

Name
Sid England
Agency Name
University of Caifornia
Contact Types
Lead/Public Agency

Location

Cities
Davis
Counties
Yolo
Cross Streets
Dairy Road and Hutchinson Drive
Zip
95616
Total Acres
0.5
State Highways
SR 113 and I-80
Railways
UPRR
Airports
University Airport
Schools
Davis Joint Unified
Waterways
Putah Creek
Township
8N
Range
2E
Section
16
Base
MD

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print