Conditional Use Permit 2004-187
2 Documents in Project
Summary
SCH Number
2005071123
Lead Agency
City of Big Bear Lake
Document Title
Conditional Use Permit 2004-187
Document Type
NOD - Notice of Determination
Received
Posted
9/7/2005
Present Land Use
Snow Play area, 14 acres, Commercial Recreation (C-4), Commercial Recreation (CR)
Document Description
The project is a three-phased development for installation of permanent improvements to the existing snow plan hill on the 14-acre property. Phase I consists of installation of a 21,000 gallon and a 4,500 gallon water holding tank, east side parking lot improvements consisting of approximately 164 spaces to serve the snow play hill, grading of the entire parking lot and portion of the snow play hill (earthwork cut-site) and construction of a 1,600 square foot building for ticket sales, restroom, and customer lounge use. Phase II improvements consist of the demolition of the existing chalet building, and construction of a 2nd and 3rd floor onto the 1,600 square foot ticket building, and Phase III consists of west side parking lot improvements consisting of approximately 91 spaces and construction of an indoor community pool or similar indoor recreational use. The precise location, size, and design of the indoor community pool or indoor recreational facility have not been determined at this date; therefore, this land use is conceptual and will require a subsequent land use and environmental review.
Contact Information
Name
Janice Etter
Agency Name
City of Big Bear Lake
Contact Types
Lead/Public Agency
Phone
Location
Cities
Big Bear Lake
Counties
San Bernardino
Cross Streets
42825 Big Bear Boulevard
Parcel #
341-461-08
State Highways
18
Airports
Big Bear City Airport
Waterways
Big Bear Lake
Notice of Determination
Approving Agency
City of Big Bear Lake Planning Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.