Winding Way Culvert Replacement and Road Improvements Project (Lake or Streeambed Alteration Agreement No. 1600-2017-0576-R3)

5 Documents in Project

Summary

SCH Number
2005062052
Lead Agency
City of San Carlos
Document Title
Winding Way Culvert Replacement and Road Improvements Project (Lake or Streeambed Alteration Agreement No. 1600-2017-0576-R3)
Document Type
NOD - Notice of Determination
Received
Posted
3/26/2018
Present Land Use
PLU: Vacant, Pre-zoned to R-1 Z: L-D GPD: Low Density Residential 3 d.u./acre)
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0576-R3, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Ron Grove. The project is limited to the replacement of an existing culvert, installation of three new culverts and road improvements to facilitate development of 5 single family homes on two acres of property. The first and most downstream culvert will be a 40-foot long high- density polyethylene pipe (HDPE) 12 inches in diameter with rip rap outfall. The second culvert will also be an HDPE pipe, approx. 50 feet long installed 18 inches below the road, with rip rap outfall. The third culvert will be a 30-inch diameter HDPE pipe, approx. 80 feet long with concrete head walls at the inlet and outlet.

Contact Information

Name
Randi Adair
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
San Carlos
Counties
San Mateo
Cross Streets
Chesham Avenue, Wingate Avenue and Winding Way
Zip
94070
Total Acres
3.41
Parcel #
49-020-010; 49-141-660-690
State Highways
101, 280
Railways
Caltrain
Airports
SFO, San Carlos Airport
Waterways
Pulgas Creek, San Francisco Bay
Township
5S
Range
4W

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print