Winding Way Culvert Replacement and Road Improvements Project
5 Documents in Project
Summary
SCH Number
2005062052
Lead Agency
City of San Carlos
Document Title
Winding Way Culvert Replacement and Road Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
6/30/2014
Present Land Use
PLU: Vacant, Pre-zoned to R-1
Z: L-D
GPD: Low Density Residential 3 d.u./acre)
Document Description
The project is limited to the replacement of an existing culvert, installation of two new culverts and road improvements to facilitate development of 5 single family homes on two acres of property. The first and most downstream culvert will be a 40-foot long high-density polyethylene pipe (HDPE) 12-inches in diameter. A five-foot by five-foot rock rip rap sized from four to six-inches in diameter will be installed at the 12-inch by 12-inch tee outfall. The pipe will be installed approximately 18 inches below the road. The second culvert will also be an HDPE pipe, approximately 50 feet long installed 18 inches below the road. The same type of dissipater as the first culver will be constructed at this outfall. The third culvert is a 30-inch diameter HDPE pipe. This will replace the existing failing culvert that is causing severe erosion in the canyon. The culvert will be approximately 80 feet long and a concrete head wall will be constructed at the inlet and outlet. The existing dirt road which accesses the property will be widened to 22 feet and paved. The California Department of Fish and Wildlife (CDFW) is executing a Lake and Streambed Alteration Agreement Number 1600-2013-0166-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Ron Grove.
Contact Information
Name
Suzanne DeLeon
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Carlos
Counties
San Mateo
Cross Streets
Chesham Avenue, Wingate Avenue and Winding Way
Zip
94070
Total Acres
3.41
Parcel #
49-020-010; 49-141-660-690
State Highways
101, 280
Railways
Caltrain
Airports
SFO, San Carlos Airport
Waterways
Pulgas Creek, San Francisco Bay
Township
5S
Range
4W
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.