Daoud Minor Subdivision; TPM 20832, Log No. 04-14-014
Document Type
NOD - Notice of Determination
Received
Posted
9/26/2005
Present Land Use
A70 - Limited Ag and General Plan 17 - Estate Residential
Document Description
The project proposes a minor subdivision of 24.19 acres into three parcels. Parcel 1 will measure approximately 9 acres net, Parcel 2 will measure approximately 4.06 acres net, and Parcel 3 will measure approximately 8.05 acres net. The project proposes grading consisting of a balance cut/fill operation of 7,800 cubic yards for three future single-family residences. The project site is located east of I-8 off of Chocolate Summit Dive in the Alpine Community Planning Group, and unincorporated area in the County of San Diego. The project is located in the Multiple Species Conservation Program (MSCP) and in the Pre-Approved Mitigation Area (PAMA). The project is subject to the Regional Land Use Element 1.3 Estate Development Area (EDA). The regional designation is (17) Estate Residential. The current zone for the property is A 70, which is Limited Agricultural. Per Section 2702(a) of the Zoning Ordinance, A 70 allows residential uses. All three proposed parcels will be serviced by the Padre Dam Municipal Water District.
Contact Information
Name
Gail Wright
Agency Name
San Diego County Department of Planning and Land Use
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Diego
Cross Streets
16390 Alpine Boulevard
Parcel #
402-350-42, 405-351-06
State Highways
Old Hwy. 80
Township
15S
Range
2E
Section
19
Base
SBM
Other Location Info
City/Community: Alpine
Notice of Determination
Approving Agency
County of San Diego Director of Planning and Land Use
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.