Camino Del Rio Extension
8 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2005061051
- Lead Agency
- Orange County
- Document Title
- Camino Del Rio Extension
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/26/2015
- Present Land Use
- Transportation, Residential, Landfill, Open Space
- Document Description
- The project will extend Camino del Rio as a four lane roadway with two lanes in either direction from its existing terminus in the Forster Ranch Community of San Clemente to La Pata Avenue. Camino Del Rio exists as a secondary four-lane roadway from Camino De Los Mares to its terminus east of Calle Precipicio. The plans for the Camino Del Rio extension include 8 ft bike lanes and 5 ft sidewalks on both sides of the roadway. Two 10 space off street parking areas immediately adjacent to the Camino Del Rio extension will be constructed east of the existing Camino Del Rio terminus.
- Contact Information
-
Darren Bradford
RWQCB - San Diego
Lead/Public Agency
2375 Northside Drive
San Diego, CA 92108
Phone : (619) 521-3356
Location
- Cities
- San Clemente
- Counties
- Orange
- Cross Streets
- Camino Del Rio and Calle Saluda
- Total Acres
- ~157
- Parcel #
- Various
- State Highways
- SR-74 (Ortega Highway)
- Schools
- San Juan Hills High
- Waterways
- San Juan Creek
- Township
- many
- Range
- many
- Section
- many
- Base
- many
Notice of Determination
- Approving Agency
- RWQCB - San Diego
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- 2375 Northside Drive, San Diego, CA 92108
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- Yes
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.