Easton Creek Sewer Rehabilitation Project, City Project No. 81150

3 Documents in Project

Summary

SCH Number
2005052091
Lead Agency
City of Burlingame
Document Title
Easton Creek Sewer Rehabilitation Project, City Project No. 81150
Document Type
NOD - Notice of Determination
Received
Posted
6/23/2005
Present Land Use
Single family residential R-1
Document Description
The project consists of installing a bypass line to divert major portion of the sewer away from Easton Creek between Alvarado Avenue and Vancouver Avenue. Downstream of the new bypass, wastewater from the residential areas in Hillsborough and Burlingame will continue to flow by gravity into the Easton Creek sewer main. The existing liner inside the 12" pipe in Easton Creek is structurally in good condition. Work in the creek will include replacing 32 sewer laterals and sealing of existing 29 manholes. A 6" liner and a 12" liner will be installed where these two collector systems tie into Easton Creek sewer main to reduce inflow and infiltration.

Contact Information

Name
Donald Chang
Agency Name
City of Burlingame
Contact Types
Lead/Public Agency

Location

Cities
Burlingame
Counties
San Mateo
Cross Streets
Alvarado Avenue / Vancouver Avenue
Zip
94010
Total Acres
2
State Highways
280
Schools
Mercy HS
Waterways
Easton Creek
Other Location Info
Easton Creek between Alvarado Avenue and Vancouver Avenue, Easton Drive between Alvarado Avenue and El Camino Real.

Notice of Determination

Approving Agency
City of Burlingame
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.