Mission Springs Water District's Painted Hills Water System Renovation Project

2 Documents in Project

Summary

SCH Number
2005051062
Lead Agency
Mission Springs Water District
Document Title
Mission Springs Water District's Painted Hills Water System Renovation Project
Document Type
NOD - Notice of Determination
Received
Posted
6/24/2005
Document Description
New development has been approved and is being constructed in MSWD's Gateway Reservoir (1530) Pressure Zone. The approved developments will require additional water availability in the Gateway Pressure Zone. The proposed project will move water supplies to the Gateway Reservoir via the existing Overhill and Valley View Reservoirs, two new booster stations at each of these reservoirs, and new and existing pipeline infrastructure will be used to transport water. Both booster stations will be located within existing fenced MSWD compounds at the Valley View and Hilltop sites. A new water pipeline will be located in Salton View Road between the Overhill and Gateway reservoirs.

Contact Information

Name
Milagros Wallace
Agency Name
Mission Springs Water District
Contact Types
Lead/Public Agency

Location

Cities
Desert Hot Springs
Counties
Riverside
Cross Streets
Pipeline will be located w/in ROW of Pierson Road State Highway 62 and Little Morongo Road
Parcel #
688-212-013; 668-040-010
State Highways
62
Township
2, 3S
Range
4E
Section
5, 6,
Base
SBM
Other Information
Section: 32

Notice of Determination

Approving Agency
Mission Springs Water District
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print