Approval of Corrective Measures Study Report that Would Allow the U.S. Dept. of Energy and Lawrence Berkeley National Lab to Implement Corrective Measures

2 Documents in Project

Summary

SCH Number
2005042160
Lead Agency
Department of Toxic Substances Control
Document Title
Approval of Corrective Measures Study Report that Would Allow the U.S. Dept. of Energy and Lawrence Berkeley National Lab to Implement Corrective Measures
Document Type
NOD - Notice of Determination
Received
Posted
9/8/2005
Present Land Use
Institutional

Document Description
Four areas of soil contamination and eleven areas of groundwater contamination are evaluated in the CMS Report. Different cleanup technologies are recommended in the CMS Report for areas with soil contamination and areas of groundwater contamination. The primary technologies for soil cleanup are excavation and off-site disposal of contaminated soil. The primary technologies recommended for groundwater are in situ flushing and monitored natural attenuation.

Contact Information
Waqar Ahmad
Department of Toxic Substances
Lead/Public Agency
700 Heinz Avenue, Building F, Suite 200
Berkeley, CA 94710

Phone : (510) 540-3932

Location

Cities
Berkeley Oakland
Counties
Alameda
Cross Streets
Cyclotron Road
Zip
94720
Total Acres
200
State Highways
13
Railways
Amtrak
Schools
UC and Berkeley HS

Notice of Determination

Approving Agency
Department of Toxic Substances
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
Department of Toxic Substances

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.