Folsom Lake Temperature Control Device

4 Documents in Project

Summary

SCH Number
2005042088
Lead Agency
El Dorado Irrigation District
Document Title
Folsom Lake Temperature Control Device
Document Type
NOD - Notice of Determination
Received
Posted
9/22/2005
Present Land Use
The project is within the Folsom State Recreational Area on US Bureau of Reclamation Land managed by State Department of Parks and Recreation.
Document Description
El Dorado Irrigation District, in collaboration with the US Bureau of Reclamation, proposes to construct facilities on the bank of Folsom Lake to withdraw water from the warm upper reaches of the lake while preserving the cold water pool at the bottom of the lake to protect downstream aquatic species. The facilities will include a large diameter concrete lined vertical shaft and five lined horizontal adits extending from the shaft. This structure, known as a Temperature Control Device (TCD) will replace the District's five existing raw pump casings that currently extract water from Folsom Lake at a rate of 19.5 MGD. The new facility will be sized to accommodate a maximum extraction rate of 74 MGD over an 18-hr period, which is equivalent to 52 MGD.

Contact Information

Name
Wayne Hubbard
Agency Name
El Dorado Irrigation District
Contact Types
Lead/Public Agency

Location

Counties
El Dorado
Cross Streets
At the end of Planeta Way adjacent to Folsom Lake
Total Acres
18.2
Waterways
Folsom Lake
Township
10N
Range
8E
Section
10
Other Location Info
El Dorado Hills

Notice of Determination

Approving Agency
El Dorado Irrigation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print