Shelter Cove Breakwater Rehabilitation
4 Documents in Project
Summary
SCH Number
2005042024
Lead Agency
Humboldt Bay Harbor
Document Title
Shelter Cove Breakwater Rehabilitation
Document Type
NOD - Notice of Determination
Received
Posted
11/14/2006
Present Land Use
Coastal-Dependent Commercial Recreation
Document Description
The Humboldt Bay Harbor, Recreation, and Conservation District proposes to rehabilitate in-place the existing Shelter Cove breakwater to restore its effectiveness. The project is located on the coastline of southern Humboldt County. Since its completion in the late 1970s, the rock breakwater has settled and lost rocks as a result of wave action, such that the breakwater is largely under water at high tide and its effectiveness at protecting the boat launching facility has been greatly compromised. The proposed project is Alternative 1 described in the Engineering Feasibility Study conducted for the project. Alternative 1 will repair the breakwater in essentially its current configuration to provide similar dimensions, level of protection, and protected area as it did originally prior to its deterioration to its current condition. The rehabilitated breakwater will be sturdier than the original to better withstand wave forces.
Contact Information
Name
David Hull
Agency Name
Humboldt Bay Harbor, Recreation and Conservation District
Contact Types
Lead/Public Agency
Phone
Location
Counties
Humboldt
Regions
Unincorporated
Cross Streets
Shelter Cove Road at the Pacific Ocean
Zip
95589
Total Acres
1
Parcel #
State Tideland
Airports
Shelter Cove
Waterways
Pacific Ocean
Township
5S
Range
1E
Section
16
Base
Humboldt
Other Location Info
Shelter Cove
Notice of Determination
Approving Agency
Humboldt Bay Harbor, Recreation, and Conservation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.