Marine Corps Air Station (MCAS) Miramar Airport Land Use Compatibility Plan (ALUCP)
6 Documents in Project
Summary
SCH Number
2005031148
Lead Agency
San Diego County Regional Airport Authority
Document Title
Marine Corps Air Station (MCAS) Miramar Airport Land Use Compatibility Plan (ALUCP)
Document Type
NOD - Notice of Determination
Received
Posted
10/7/2008
Present Land Use
Planning designations vary throughout the MCAS Miramar ALUCP's airport influence area.
Document Description
The proposed project is the Marine Corps Air Station (MCAS) Miramar Airport Land Use Compatibility Plan (ALUCP). The San Diego County Regional Airport Authority, acting as the Airport Land Use Commission for the County of San Diego, is required by law to adopt an ALUCP for "area[s] within the jurisdiction of the [ALUC] surrounding any military airport." (Pub. Util. Code, §21675, subd. (b).) The MCAS Miramar site lies within the jurisdiction of the ALUC.
The basic function of an ALUCP is to promote compatibility between an airport and the land uses that surround the airport and lie within the airport's designated airport influence area, to the extent that these areas are not already devoted to incompatible uses.
Contact Information
Name
Keith Wilschetz
Agency Name
San Diego County Regional Airport Authority
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Diego
Counties
San Diego
Cross Streets
Interstate 15 and Miramar Road
Zip
92145
State Highways
I-15
Airports
MCAS Miramar
Notice of Determination
Approving Agency
San Diego County Regional Airport Authority
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes