Carrillo Street Northbound On-Ramp Widening

2 Documents in Project

Summary

SCH Number
2005031063
Lead Agency
California Department of Transportation, District 5
Document Title
Carrillo Street Northbound On-Ramp Widening
Document Type
NOD - Notice of Determination
Received
Posted
6/29/2005
Present Land Use
State Highway Corridor within the project limits and just beyond are Commercial and Residential
Document Description
Caltrans proposes to improve operations at the intersection of Carrillo Street and the northbound 101 on-ramp. The project would widen the Carrillo Street northbound on-ramp at Route 101 to two lanes and install ramp metering with a California Highway Patrol (CHP) enforcement area. The on-ramp would contain a 4.0-foot wide inside shoulder, two 12-foot wide travel lanes and an 8-foot wide outside shoulder. The project includes the removal of a portion of the existing landscaping between the ramp and concrete channel. A retaining wall would be constructed to accommodate the additional lane for the on-ramp. Re-landscaping would occur once the on-ramp is completed.

Contact Information

Name
Yvonne Hoffmann
Agency Name
Department of Transportation, District 5
Contact Types
Lead/Public Agency

Location

Cities
Santa Barbara
Counties
Santa Barbara
Cross Streets
Carrillo Street and Route 101
Total Acres
1.8
Parcel #
Caltrans right of way
State Highways
101
Railways
Union Pacific
Schools
Harding School and Peabody School
Waterways
Mission Creek

Notice of Determination

Approving Agency
California Department of Transportation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print