Document Description
The scope of the project is to create two key water supply facilities - a Flow Control Facility at the Metropolitan Water District OC-72 Turnout, and a Zone 3-4 Booster Pump Station. The schedule provides for construction of the facilities by April 2006, in time to supply water for first occupancy in the first phase of development. The Booster Pump Station will be housed inside a single level building, which consists of two rooms, a 25-foot by 4-inch by 44-foot pump room, and a separate 8-foot, 8-inch by 25-foot, 4-inch electrical room. The Flow Control Facility will be comprised of reconfigured piping and appurtenances, some of which are existing and some of which will be newly constructed to redirect flow. Most of the newly constructed flow control facility will be above grade. The Zone 4 Flow Control Facility at OC-72 and the Zone 3-4 Booster Pump Station will each be sized to meet the maximum day demand for the entire PA 6 development.

Contact Information

Name
Gregory K. Herr
Agency Name
Irvine Ranch Water District
Contact Types
Lead/Public Agency

Location

Cities
Irvine
Counties
Orange
Cross Streets
Portola Parkway
Total Acres
1.5
Jobs
7
State Highways
133 Eastern and 241 Foothill

Notice of Determination

Approving Agency
Irvine Ranch Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A