University of California Santa Cruz Building Expansion Projects
13 Documents in Project
Summary
SCH Number
2005012113
Lead Agency
University of California Santa Cruz
Document Title
University of California Santa Cruz Building Expansion Projects
Document Type
NOD - Notice of Determination
Received
Posted
3/7/2007
Document Description
The project consists of improvements to existing storm water, cooling water, and domestic/fire water infrastructure at numerous locations on the campus, to address existing inadequacies and to remediate erosion and potential water quality problems in campus drainages. Elements include construction of a new cooling tower, replacement of several domestic/fire pipeline segments, and installation of about 1,000 linear feet of new cooling water pipelines, primarily in existing roadways or shoulders. Stormwater improvements will include retrofit of existing drains, installation of features to reduce runoff velocity, and installation of dissipation and infiltration features to reduce runoff volume. The project was analyzed in the UC Santa Cruz 2005-2020 Long Range Development Plan EIR, which was certified by the Regents of the University of California in September 2006.
Contact Information
Name
Sally Morgan
Agency Name
University of California, Santa Cruz
Contact Types
Lead/Public Agency
Phone
Location
Cities
Santa Cruz
Counties
Santa Cruz
Cross Streets
Bay Street / High Street
Zip
95064
Parcel #
01-011-13
State Highways
1, 9, 17
Schools
UC Santa Cruz
Township
11S
Range
2W
Section
10
Base
SC
Notice of Determination
Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.