Physical Sciences Expansion and Service Unit Park

3 Documents in Project

Summary

SCH Number
2005012057
Lead Agency
University of California, Davis
Document Title
Physical Sciences Expansion and Service Unit Park
Document Type
NOD - Notice of Determination
Received
Posted
3/18/2005
Present Land Use
Physical Sciences Expansion Site designated Academic and Administrative; Service Unit Park designated Research Park.
Document Description
The site for the proposed facility is located in the central core of the UC Davis campus on the southwest portion of the current Operations and Maintenance (O&M) services site. The project requires the removal of a portion of the O&M facilities and other buildings. This project will include teaching and research facilities for programs in the physical sciences. The PSE contains 51,250 assignable sf within a total area of 88,362 gsf. The project will provide space for the Departments of Geology, Chemistry, and Physics comprised of instructional laboratories and service, research laboratories/offices and service, and departmental office support space. It will replace obsolete and inadequate teaching and research laboratories, consolidate like activities in a new building, and allow reassignment of existing space to the Dept. of Physics.

Contact Information

Name
John E. Zimmermann
Agency Name
University of Caifornia
Contact Types
Lead/Public Agency

Location

Cities
Davis
Counties
Yolo
Cross Streets
La Rue Road / California Avenue / Hopkins Road
Zip
95616
Total Acres
27
Parcel #
N/A
State Highways
SR 113, I-80
Railways
UPRR
Airports
University Airport
Schools
Davis Joint Unified
Waterways
Putah Creek
Township
8N
Range
2E
Section
16, 18
Base
Diablo

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.