City of Roseville Northeast Water Storage Reservoir Replacement Project

3 Documents in Project

Summary

SCH Number
2005012018
Lead Agency
City of Roseville
Document Title
City of Roseville Northeast Water Storage Reservoir Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
1/22/2007
Present Land Use
The project site currently supports the City of Roseville's Northeast Tank Facility. The project site is located within the corporate boundaries of the City of Rocklin, but because it is owned by the City of Roseville, it is subject to Rosevills' land use ordinances, goals and policies.
Document Description
The applicant is proposing to replace a six million gallon capacity (MG) seismically-deficient treated water storage reservoir with a new 7.25 MG replacement reservoir. The 7.25 MG replacement reservoir would be constructed adjacent to the existing 6 MG tank within the City of Roseville's Northeast Tank Facility. Although the facility site is owned by the City of Roseville, the site is located within the City of Rocklin's corporate boundaries, immediately adjacent to the Roseville corporate boundary. The replacement reservoir would be designed to meet current seismic codes. The height and volume of the new reservoir would be similar to that of the existing reservoir. Upon completion of the new tank, the existing tank would be demolished and removed.

Contact Information

Name
Cathy Lee
Agency Name
City of Roseville
Contact Types
Lead/Public Agency

Location

Cities
Rocklin
Counties
Placer
Cross Streets
Scarborough Drive/Ballantrae Way, 1201 Scarborough Drive
Zip
95661
Total Acres
8
Parcel #
na
State Highways
I-80
Railways
Union Pacific
Airports
na
Schools
Sierra & Stonebridge Elementary
Waterways
Miners Ravine (Dry Creek)

Notice of Determination

Approving Agency
Roseville City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.