Santa Margarita River Conjunctive Use Project - Water Rights Petitions

9 Documents in Project

Summary

SCH Number
2004121068
Lead Agency
Fallbrook Public Utility District
Document Title
Santa Margarita River Conjunctive Use Project - Water Rights Petitions
Document Type
NOD - Notice of Determination
Received
Posted
11/21/2018
Present Land Use
Military Base A-70
Document Description
Fallbrook Public Utility District (FPUD) filed petitions for a 50-year extension of time to complete construction and beneficial use of water under water right Permits 8511, 11375, and 21471B. FPUD also filed change petitions for the water right Permits and License 10494 to abandon its authorized two-dam project and add direct diversion, underground storage and offstream storage, and to consolidate the purposes and places of use amond the Permits and License, to facilitate the Santa Margarita River Conjunctive User Project. The project will provide a physical solution to the long-term rights litigation between FPUD and Camp Pendleton.

Contact Information

Name
Sean Maguire
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Fallbrook
Counties
San Diego
Cross Streets
Ammunition and Alturas
Parcel #
104-190-17, -04
Railways
No
Airports
Fallbrook
Schools
Mary Fay Pendleton School
Waterways
Fallbrook Creek
Township
9S
Range
4W
Section
25
Base
SBB&M
Other Location Info
Marine Corps Base Camp Pendleton

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.