Santa Margarita River Conjunctive Use Project
9 Documents in Project
Summary
SCH Number
2004121068
Lead Agency
Fallbrook Public Utility District
Document Title
Santa Margarita River Conjunctive Use Project
Document Type
NOD - Notice of Determination
Received
Posted
10/7/2016
Present Land Use
Military Base A-70
Document Description
The proposed project would upgrade an existing groundwater recharge and recovery system to help meet water demands for Camp Pendleton and Fallbrook, reduce regional dependency on imported water, and improve water reliability. Project elements would improve existing facilities, replace existing structures, and/or construct new facilities. The proposed project would include diversion system upgrades, groundwater recharge, and groundwater production. Raw groundwater would be delivered to FPUD via a new bi-directional pipeline for treatment in a new water treatment plant constructed on FPUD property adjacent to DET Fallbrook and operated by FPUD.
Contact Information
Name
Jack Bebee
Agency Name
Fallbrook Public Utility District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Fallbrook
Counties
San Diego
Cross Streets
Ammunition and Alturas
Parcel #
104-190-17, -04
Railways
No
Airports
Fallbrook
Schools
Mary Fay Pendleton School
Waterways
Fallbrook Creek
Township
9S
Range
4W
Section
25
Base
SBB&M
Other Location Info
Marine Corps Base Camp Pendleton
Notice of Determination
Approving Agency
Fallbrook Public Utility District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.