South Sacramento Streams Project

3 Documents in Project

Summary

SCH Number
2004102009
Lead Agency
Sacramento Area Flood Control Agency
Document Title
South Sacramento Streams Project
Document Type
NOD - Notice of Determination
Received
Posted
2/25/2005
Document Description
The project is designed to provide flood protection measures capable of conveying flows of a 100-year flood event on the following waterways: Morrison Creek downstream of Stockton Boulevard, Elder Creek downstream of Stockton Boulevard, and Unionhouse Creek downstream of Center Parkway. Flood protection would be accomplished by excavating the select stream channels, retrofitting stream passage beneath several local bridge crossings, installing floodwalls at select locations, realigning portions of existing levees, and installing box culverts at several stream crossings. These measures, when combined, would increase the capacity of these streams to convey a 100-year flood event and meet FEMA criteria.

Contact Information

Name
Grant Kreinberg
Agency Name
Sacramento Area Flood Control Agency
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
SR-99 / I-5 / Florin Road / Stockton Boulevard
Total Acres
N/A
State Highways
SR 99, I-5
Railways
UPRR
Waterways
Morrison, Elder, Florin, and Unionhouse Creeks

Notice of Determination

Approving Agency
Sacramento Area Flood Control Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print