Mark Welch Reservoir; IS 04-56, MUP 04-51

2 Documents in Project

Summary

SCH Number
2004092015
Lead Agency
Lake County
Document Title
Mark Welch Reservoir; IS 04-56, MUP 04-51
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2004
Present Land Use
GP: Agriculture Z: Agriculture
Document Description
The applicant proposes to construct a 42.6 acre foot off-stream reservoir to use for irrigating vineyards. Approximately 2.9 acres of land will be cleared and approximately 46,300 cubic yards of material will be excavated to create the reservoir. All excavated material will remain onsite to create an embankment and to spread on adjacent vineyard. The embankment will be 12 feet in height. Water from an existing well will be pumped into the reservoir. The project site has already been cleared as part of the previously approved vineyard development, and is outside the protected areas for blue elderberry shrubs and konocti manzanita as indicated in the biological assessment and botanical survey prepared by Northwest Biosurvey dated June 15, 2001 for the vineyard development. The project is located outside the documented archaeological site on the property.

Contact Information

Name
Melissa Banks
Agency Name
Lake County Community Development Department
Contact Types
Lead/Public Agency

Location

Counties
Lake
Cross Streets
S. State Hwy 29 / Conservation Camp Road
Zip
95457
Total Acres
2.9
Parcel #
009-006-37; 011-009-35
State Highways
29
Waterways
Thurston Creek
Township
12/13N
Range
8W
Section
2, 35
Base
Diablo
Other Location Info
City: Lower Lake
Other Information
Township: 12N, 13N

Notice of Determination

Approving Agency
Lake County Community Development Department
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print