Mark Welch Reservoir; IS 04-56, MUP 04-51
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2004
Present Land Use
GP: Agriculture
Z: Agriculture
Document Description
The applicant proposes to construct a 42.6 acre foot off-stream reservoir to use for irrigating vineyards. Approximately 2.9 acres of land will be cleared and approximately 46,300 cubic yards of material will be excavated to create the reservoir. All excavated material will remain onsite to create an embankment and to spread on adjacent vineyard. The embankment will be 12 feet in height. Water from an existing well will be pumped into the reservoir. The project site has already been cleared as part of the previously approved vineyard development, and is outside the protected areas for blue elderberry shrubs and konocti manzanita as indicated in the biological assessment and botanical survey prepared by Northwest Biosurvey dated June 15, 2001 for the vineyard development. The project is located outside the documented archaeological site on the property.
Contact Information
Name
Melissa Banks
Agency Name
Lake County Community Development Department
Contact Types
Lead/Public Agency
Phone
Location
Counties
Lake
Cross Streets
S. State Hwy 29 / Conservation Camp Road
Zip
95457
Total Acres
2.9
Parcel #
009-006-37; 011-009-35
State Highways
29
Waterways
Thurston Creek
Township
12/13N
Range
8W
Section
2, 35
Base
Diablo
Other Location Info
City: Lower Lake
Other Information
Township: 12N, 13N
Notice of Determination
Approving Agency
Lake County Community Development Department
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes