Palco Marsh Enhancement Plan - Phase 1A Work Plan

3 Documents in Project

Summary

SCH Number
2004082028
Lead Agency
City of Eureka
Document Title
Palco Marsh Enhancement Plan - Phase 1A Work Plan
Document Type
NOD - Notice of Determination
Received
Posted
9/9/2004
Present Land Use
Z: Natural Resources and Coastal Dependent Industrial GP: Natural Resources and Coastal Dependent Industrial
Document Description
The project includes the installation of a 48-inch culvert to replace an existing 24-inch culvert connecting Palco Marsh with Humboldt Bay; aesthetic modification of the Del Norte Street drainage structure, removal of silt from the structure and replacement and/or removal of existing tide gates; hand digging and cleaning of Palco Marsh channels; dredging of the tidal slough between Palco Marsh and the peninsula west of the marsh; installation of Del Norte and Felt Streets landscaping; installation of interpretive signage; eradication of common reed and other invasive exotics; revegetation of treated common reed areas; and the hydrologic enhancement of Railroad Marsh. The plan also includes monitoring, maintenance and management activities including botanical and hydrologic monitoring; monitoring and treatment of exotics; monitoring and removal of sediment from marsh channels and the tidal channel; repair, maintenance or replacement of existing drainage structures; and monitoring and clean-up of garbage.

Contact Information

Name
Lisa D. Shikany
Agency Name
City of Eureka
Contact Types
Lead/Public Agency

Location

Cities
Eureka
Counties
Humboldt
Cross Streets
Del Norte Street / Felt Street / Vigo Street
Total Acres
~ 86
Railways
NCRA

Notice of Determination

Approving Agency
City Council of the City of Eureka
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.