Culvert replacement and dissipater installation on bank of Casserly Creek

Summary

SCH Number
2004079025
Lead Agency
Fish & Game #3
Document Title
Culvert replacement and dissipater installation on bank of Casserly Creek
Document Type
NOD - Notice of Determination
Received
Posted
7/6/2004
Document Description
This project consists of the replacement of a culvert fro the existing 12" size to an 18" culvert that drains into Casserly Creek. The overall project is the construction of a one-story Fire Station, about 250 feet south of the intersection of Casserly Road and Mt. Maddona Road. A 6' wide by 9' high by 1' deep angular rock dissipater will be placed on the bank. The culvert will include a "T" water release devise above the stream channel elevation. The existing eroded bank will be filled with compacted materials. The existing shrub and grass vegetation up to (if needed) 15 feet either side of the center line of the culvert will be removed to allow dissipater construction. The CDFG is executing a Lake and Streambed Alteration Agreement Number 1600-2004-0234-3 Pursuant to Section 1602 of the Fish and Game Code to the Project Operator, Chief Greg Estrada/Pajaro Valley Fire Protection District.

Contact Information

Name
Serge Glushkoff
Agency Name
Department of Fish and Game, Region 3
Contact Types
Lead/Public Agency

Location

Counties
Santa Cruz

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.