Cuyamaca Forest Fire Station Relocation Project

3 Documents in Project

Summary

SCH Number
2004071130
Lead Agency
Forestry and Fire Protection, Department of (Cal Fire)
Document Title
Cuyamaca Forest Fire Station Relocation Project
Document Type
NOD - Notice of Determination
Received

Document Description
The project involves the relocation of the Cuyamaca Forest Fire in San Diego County. The existing fire station within Cuyamaca Rancho State Park will be abandoned by CAL FIRE (and continue to be used by State Parks for another purpose) and a new fire station constructed a few miles further north. A Negative Declaration was prepared and a Notice of Determination was filed for the project in September 2, 2004. The project now includes a minor change to the construction of the new fire station. The change involves a slightly expanded graded area to lessen the risk for landslides, the removal of six additional oak trees originally planned to be retained on site, and possibly up to 2,500 cubic yards of soil removed where the ND assumed that earthmoving would be balanced on site. An addendum to the 2004 ND discussed the changes and CAL FIRE found based on substantial evidence in the record that changes to the project were minor and do not result in new potential impacts or the need for new mitigation measures.

Contact Information
Daniel Foster
Department of Forestry And Fire Protection
P.O. Box 944246
Sacramento, CA 944246

916 653 0839

Location

Counties
San Diego
Cross Streets
2.75 miles NE of junction of Hwy 79 and Engineers Road
Total Acres
< 5
State Highways
79
Other Location Info
City: Cuyamaca
Other Information
Within 2.75 Miles...

Notice of Determination

Approving Agency
Department of Forestry and Fire Protection
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
CA Department of General Services Real Estate Services Division 707 Third Street, 3rd Floor West Sacramento, CA

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search