Central Disposal Site Leachate and Landfill Gas Pipeline Project;

3 Documents in Project

Summary

SCH Number
2004062099
Lead Agency
Sonoma County
Document Title
Central Disposal Site Leachate and Landfill Gas Pipeline Project;
Document Type
NOD - Notice of Determination
Received
Posted
10/26/2004
Present Land Use
Construction will occur at the Sonoma County Central Disposal Site, zoned Public/Quasi-Public and within the County road right-of-way.
Document Description
The Department of Transportation and Public Works, Integrated Waste Division proposes to install two pipelines to facilitate more efficient operations at the Sonoma County Central Disposal Site. One pipeline would transport leachate from the landfill leachate ponds to the Rohnert Park sewer trunk line near Stony Point Road and the Laguna de Santa Rosa. The second pipeline would transport landfill gas from the Central Disposal Site to a PG&E connection point on Juniper Road that services the Sonoma County Transit Facility on West Robles Road. The pipelines will be located within the roadway prism and the general route will include Hammel Road, to Mecham Road, to Stony Point Road to Todd Road.

Contact Information

Name
Alynn Kjeldsen
Agency Name
Sonoma County Permit and Resources Management Department
Contact Types
Lead/Public Agency

Location

Cities
Cotati, Rohnert Park
Counties
Sonoma
Cross Streets
Hammel Road / Mecham Road / Stony Point Road / Todd Road
State Highways
116, 101
Waterways
Washoe Creek, Gossage Creek, Laguna de Santa Rosa
Base
Diablo

Notice of Determination

Approving Agency
Sonoma County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print