Oak Street to Ninth Avenue Project Draft Response Plan

15 Documents in Project

Summary

SCH Number
2004062013
Lead Agency
City of Oakland
Document Title
Oak Street to Ninth Avenue Project Draft Response Plan
Document Type
NOD - Notice of Determination
Received
Posted
7/23/2010
Document Description
The proposed project under consideration before DTSC is the approval and implementation of a Response Plan for the Oak Street to Ninth Avenue Project Area (Site). The Response Plan details the remediation of contaminated soils, soil gas, and groundwater at the Site. Oakland Harbor Partners, LLC plans to redevelop the Site into a mixed-use, waterfront, multi-family, urban residential neighborhood with a retail component surrounded by interconnecting open space. Approximately 3,100 residential units will be built and 30 acres of open space created on the Site. Remediation and redevelopment of the Site are currently designed to occur in 4 primary phases. The redevelopment of the Site is expected to occur over a period of 20 yrs. Remediation of the Site will primarily occur sequentially throughout the 4 primary phase areas identified above. The 4 primary phase areas are further divided into 12 defined Development Parcels or Open Space Parcels (i.e. a portion of a parcel that can be logically remediated and redeveloped as a stand-alone project). Remediation activities will be conducted concurrent with general Site preparation activities for redevelopment.

Contact Information

Name
Homayune Atigee
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
Embarcadero Road / Fallon Street / 10th Avenue
Zip
94607
Total Acres
64
Parcel #
0000-0430-001-02; 0000-0430-001-04; 0000-0460-003; 0000-0460-004; 0000-0465-002; 0000-0470-002
State Highways
I-880
Railways
Yes
Schools
Yes
Waterways
Oakland Estuary, SF Bay
Other Information
Zip Code: 94606

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes