Schematic Plan Approval for the Alex G. Spanos Stadium, West Bleacher and Infrastructure Improvements
3 Documents in Project
Summary
SCH Number
2004061007
Lead Agency
California State University Board of Trustees
Document Title
Schematic Plan Approval for the Alex G. Spanos Stadium, West Bleacher and Infrastructure Improvements
Document Type
NOD - Notice of Determination
Received
Posted
11/18/2004
Present Land Use
Master plan designated for stadium and parking
Document Description
The campus has prepared a project specific EIR for the anticipated build-out of the stadium site to include not only the west bleachers to add a maximum 2,080 seating capacity, but also the future addition of another maximum 4,240 seats, Parking Structure II (1,000 spaces), and an office building. The project-specific EIR also describes the demolition of portions of the stadium to build larger seating facilities, demolition of two structures designated as historic, as well as circulation improvements. The West Bleacher and Infrastructure Improvements project will increase the existing stadium seating capacity, provide concession areas, restrooms, and other support offices. The lower concourse seating will be a combination of bleacher and chair back seats. The upper concourse will have ten private boxes, which includes the press box and coaches' box. Two elevators will provide access to the upper concourse. The project will improve the playing field, provide hardscape and landscape areas, and nine surface parking spaces, all of which are accessible.
Contact Information
Name
Robert Kitamura
Agency Name
California State Board of Trustees
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
California Boulevard / Campus Way
Zip
93407
Total Acres
9
Parcel #
073-341-020
State Highways
1, 101
Railways
UPRR
Schools
University
Waterways
Brizzolara Creek
Notice of Determination
Approving Agency
Trustees of the California State University
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.