ER 2003-19 (Mitigated Negative Declaration for Nightingale Care Facility, 2003-26-CUP/GE)

3 Documents in Project

Summary

SCH Number
2004051126
Lead Agency
City of Escondido
Document Title
ER 2003-19 (Mitigated Negative Declaration for Nightingale Care Facility, 2003-26-CUP/GE)
Document Type
NOD - Notice of Determination
Received
Posted
11/27/2007
Present Land Use
R-1-10 (Single-Family Residential, 10,000 SF min. lot size) Suburban General Plan Designation (Single-Family Residential)
Document Description
A Conditional Use Permit originally was approved by the Planning Commission in 2003 for a 74,903 square foot, two- and three-story residential-care facility for up to 165 clients/residents on the 3.48-acre site. The facility is proposed to be constructed in two phases (Phase 1 - Assisted Living Component; Phase 2 - Skilled Nursing Component). The permit was modified in 2004 (Case No. 2004-61-CUP) to construct a separate 900 square foot (36' x 25'), seven to nine-foot-high mechanical enclosure area to accommodate a variety of mechanical equipment, trash bins, and a 132 kW emergency standby generator. The permit was modified again in 2007 (Case No. 2007-33-CUP) to revise the enclosure design and construct a 2,478 square foot, two-story central plant building. Several modifications to the site/grading plans, retaining wall design and relocation of the equipment area also are necessary to accommodate current Fire Department access requirements within the southern parking area/drive aisle, and to remove the portion of the retaining wall that was planned to be constructed over an existing public sewer line.

Contact Information

Name
Jay Paul
Agency Name
City of Escondido
Contact Types
Lead/Public Agency

Location

Cities
Escondido
Counties
San Diego
Cross Streets
Iris Lane
Zip
92026
Total Acres
3.03
Parcel #
226-190-22
State Highways
I-15
Schools
Esc. High School
Other Location Info
1802 N. Centre City Parkway

Notice of Determination

Approving Agency
City of Escondido
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes