Mojave River West Levee Improvement Project

5 Documents in Project

Summary

SCH Number
2004051049
Lead Agency
San Bernardino Flood Control District
Document Title
Mojave River West Levee Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/22/2004
Present Land Use
Floodway
Document Description
Project will provide concrete rock slope protection to existing west levee of Mojave River. Some portions of the levee may increase up to 4 feet in height to meet design standards for containing 100-year flood. Slope protection will consist of concreted rock installed from approx. 10 ft. below channel bed surface to top of levee bank. Portions of stand of cottonwood trees will be removed to allow construction equipment to access existing earthen levee. The project was identified and discussed in the Floodplain Maintenance Plan (FMP) which provided for mitigation measures for temporary impacts to existing vegetation and riparian habitat used by protected species. The proposed improvements are needed to protect existing properties and residences located just west of the Mojave River from potential 100-year floods.

Contact Information

Name
Naresh P. Varma, P.E.
Agency Name
Department of Public Works
Contact Types
Lead/Public Agency

Location

Cities
Victorville
Counties
San Bernardino
Cross Streets
I-15 Freeway
Zip
92394
State Highways
18
Railways
BNSF & UP
Schools
Several Victorville USD schools
Waterways
Mojave River
Township
5N
Range
4W
Section
3

Notice of Determination

Approving Agency
San Bernadino County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.