Document Description
SEA/EIR Addendum IP 16-378 has been prepared by the Corps and OC Flood Control District (OCFCD) as a supplemental document to the approved FSEIS/EIR for the SARI Line Protection/Relocation Project, certified Oct. 2009. This SEA/EIR Addendum, satisfying requirements for both NEPA and CEQA documentation, addresses two new or revised project elements: 1. Pipe Severing Element - After the SARI Line was relocated, the abandoned segment was filled with cellular concrete and the tops of the manhole cones that accessed the abandoned line were removed. As part of the Proposed Action, the abandoned pipeline section will now be severed in the place to complete the abandonment process. This project element consists of severing the abandoned SARI pipeline on each side of five river channel crossings, for a total of ten severing sites. This project element involves severing the abandoned SARI pipeline on the river side of each old manhole location at each crossing without entering the active channel and without removing any of the abandoned pipeline. Construction access to the severing locations would utilize existing access/maintenance roads. 2. Manhole Protection Element - This project element involves the installation of manhole protection that will be constructed as part of the Corps' Lower SAR, Reach 9 Phase 5B bank improvement project along the river side of La Palma Ave. in the City of Yorba Linda. The Manhole Protection Element of the Proposed Action consists of installing foundation protection of the YLS wastewater pipeline (an 18-inch diameter vitrified clay pipe [VCP] with concrete encasement). The proposed protection for the manholes and the adjacent section of the YLS sewer line would tie in to the planned bank revetment.

Contact Information
Chris Uzo-Diribe
Orange County
300 N. Flower Street.
Santa Ana, CA 92702

714-667-8845

Location

Coordinates
33°52'16"N 117°40'30"W
Cities
Yorba Linda
Counties
Orange
Cross Streets
Weir Canyon Road, La Palma Avenue, Green River Golf Club
Zip
92887
Total Acres
2.5
Parcel #
Many
State Highways
Hwy 71, 91, 241
Railways
BNSF
Waterways
Santa Ana River
Township
3S
Range
8W
Section
36
Base
SBB&M
Other Information
Section Continued: 32

Notice of Determination

Approving Agency
County of Orange
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
300 N Flower St., Santa Ana, CA 92702

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes