Hi-Desert Water District Warren Valley Basin Groundwater Recharge
3 Documents in Project
Summary
SCH Number
2004041119
Lead Agency
Hi-Desert Water District
Document Title
Hi-Desert Water District Warren Valley Basin Groundwater Recharge
Document Type
NEG - Negative Declaration
Received
Present Land Use
Land Uses vary, but is primarily residential.
Document Description
The project consists of the following activities: Install approximately 7,000 lineal feet of 24-inch PVC pipeline. The maximum area of surface disturbance is estimated at 140,000 sq. ft. or approximately 3.21 acres. The construction of a recharge area containing two separate basins. Each basin will be approximately 5 acres in size. Other facilities include the flow control facility, which will disturb another 3,000 sq. ft. or 0.07 of an acre of the recharge basin site surface, and approximately 555 cubic yards of soil (to a 5-foot depth). The 3 monitoring wells and one extraction well will be developed according to typical District specifications.
Contact Information
Name
Pat Grady
Agency Name
Hi-Desert Water District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Yucca Valley
Counties
San Bernardino
Total Acres
15 +
State Highways
62
Township
1 N
Range
5 E
Section
Multi.
Base
SBBM
Other Information
The proposed project is located within the Town of Yucca Valley in the County of San Bernardino. The 24-inch pipeline will begin at the intersection of Sunnyslope Drive and Sage Avenue, head due west and then southwest to the intersection of Cholla Avenue and Buena Vista Drive, and generally parallel Buena Vista Drive until it intersects with Cherokee Trail, in Township 1 North, Range 5 east and Sections 34 and 35, San Bernardino Base & Meridian (SBBM). The proposed alignment follows the existing 16-inch Four Corners Petroleum pipeline route. The pipeline length is 7,000 feet. An approximate 10-acre recharge basin site is located just to the east of Pioneertown Road and south of Buena Vista Drive, to the southeast of quarter of Section 34, Township 1 North, Range 5 east, SBBM. The recharge site is located on land owned by the District, which already has other water facilities, including Wells #2, 3, and 9.
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Conservation (DOC), California Department of Health Care Services (DHCS), California Department of Parks and Recreation, California Department of Transportation, District 8 (DOT), California Native American Heritage Commission (NAHC), California Regional Water Quality Control Board, Colorado River Basin Region 7 (RWQCB), California State Lands Commission (SLC), Department of Fish and Wildlife, Region 6, Department of Water Resources, Resources Agency, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights, State Water Resources Control Board, Divison of Financial Assistance
Development Types
Water Facilities
Local Actions
Water infrastructure
Project Issues
Air Quality, Cultural Resources, Flood Plain/Flooding, Geology/Soils, Hydrology/Water Quality, Noise, Vegetation, Wildlife
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.